Solar PV during generator testing needs an agreed operating plan, not a blanket instruction to leave it on or turn it off. The answer depends on where the PV connects, what the transfer system supplies and whether PV was designed to operate alongside the generator.
For a factory, quarry or holiday park with commercial solar and standby generator systems, establish that interface before testing. This is a job for competent electrical, PV and generator specialists, not an inverter setting change made on the day.
Map the PV, generator and transfer arrangement
Start with an up-to-date single-line diagram and relevant handover records. Identify the PV connection point, generator connection, transfer equipment and which parts of the site can be supplied by the generator. Check that records reflect later additions or alterations.
An automatic transfer switch (ATS) changes the supply feeding the circuits it serves. Its presence does not establish whether PV is connected on the generator-backed side or how PV is controlled there. The PV inverter and automatic transfer switch need reviewing together.
The drawing should be backed by inverter and generator model details, transfer-system information, control descriptions and the existing connection agreement. Have these available to the relevant specialists before the visit, especially where different contractors installed or now maintain the equipment.
Give whoever reviews the solar PV installation the same drawings as the electrical and generator teams. If the connection point or control arrangement is uncertain, resolve that before agreeing the test.
Separate loss-of-mains protection from generator operation
Conventional grid-connected PV is intended to disconnect when the public supply is lost. That loss-of-mains response does not, by itself, establish what happens once a generator supplies the part of the installation containing the inverter.
The inverter may then encounter voltage and frequency provided by the generator. Whether PV is permitted to operate in that condition is a separate design question. A normal-looking inverter display is not evidence of compatibility.
This matters when planning solar during generator changeover and the return to mains. Ask the specialists to define the expected PV response at each stage, including how unwanted reconnection is prevented where PV must remain excluded. Do not defeat protection or alter settings to make the test proceed.

Establish whether PV is excluded or designed to run
Keeping PV out of generator-backed operation and designing it to contribute are different arrangements, not two settings to select on test day. The site’s requirement should be agreed first; the documents and controls must then support that requirement.
PV excluded from generator-backed operation
The documented arrangement may keep PV unavailable while the generator supplies the site. Establish how that exclusion is achieved and what evidence will confirm it. If the test instead relies on a temporary PV shutdown, record that limitation: it does not verify the automatic behaviour of the installation during an unplanned outage.
PV designed to operate in an island
If PV is intended to operate while the public network is disconnected, that mode needs specific design evidence. Review inverter and generator compatibility, coordinated controls, protection and behaviour if either source stops. Obtain relevant manufacturer requirements and commissioning records.
PV contribution changes the load seen by the generator and can create an interaction that causes it to trip. A test at one level of sunshine and demand is not proof of suitability across the intended operating range.

Agree a shared test scope before the visit
Define whether the visit involves an engine-only run, a transfer of site loads or a check of the PV interface. These are different scopes: a run that never exposes the inverter to the generator cannot establish its response under generator supply.
For a commercial generator test with solar PV, agree responsibilities before attendance:
- Site manager – provide records, operational constraints and a named decision-maker if the agreed behaviour is not observed.
- Electrical contractor – review the transfer arrangement, source separation and relevant electrical test evidence.
- PV specialist – confirm expected inverter behaviour, control requirements and access to event records.
- Generator specialist – assess the effect of PV on generator operation and identify the operating limits relevant to the test.
Arrange access to the PV monitoring information as well as the generator record. If a separate PV maintenance provider holds relevant data or design documents, involve them before the visit rather than leaving the generator contractor to interpret an unfamiliar inverter on site.
Name one test lead to agree the expected responses, evidence to capture and conditions for stopping. A generator engine service does not automatically include assessment of the PV interface.
Check the connection position before changing modes
Testing an existing, documented and approved arrangement is different from changing its wiring, controls or operating mode. Do not assume every routine generator test requires a fresh distribution network operator (DNO) application; equally, do not treat adding PV operation on generator supply as routine testing.
The ENA’s March 2026 G98 and G99 connection guide describes customer island modes, including switched-alternative operation without parallel operation with the public network. It states that generation capable of island operation must meet G99 provisions. A ‘no parallel’ description is therefore not a reason to skip the connection review.
Where island operation is proposed, ask the designer to assess the applicable G99 provisions and the site’s connection conditions before alterations. National Grid Electricity Distribution’s South West area includes Cornwall, but confirm the distributor and any independent or private-network arrangements for the actual site.
Connection acceptance, equipment compatibility and the agreed test method answer different questions. Keep all three aligned; none should be treated as a substitute for the others.

Leave a usable record of the PV response
Keep a short interface record alongside the electrical drawings and test report. State the intended operating mode, documents reviewed, expected PV response and what was observed during transfer, generator operation and return to mains, where those stages formed part of the agreed test.
Record who assessed each element and any inverter or generator events. If daylight conditions or the agreed scope prevented verification of PV behaviour, say so explicitly.
Identify the version of drawings and control descriptions used, so a future inverter replacement or transfer-system alteration can be checked against the same basis. Store the agreed method, observations and outstanding actions together, with an owner for each follow-up item, so they remain usable when contractors or site staff change.
Where evidence is missing, define the further electrical testing and compliance work needed. A clear limitation is more useful for the next maintenance visit or PV alteration than an unqualified ‘test passed’.
Maenporth Electrical Ltd is based at Maenporth and serves Falmouth, Penryn and wider Cornwall. To discuss the electrical side of solar PV during generator testing, call 01326 250297. Have existing drawings and equipment details ready if available.